One task, one resource, different work per work

K

Kay

Dear all,
I have one resource, one task.
the resource shall work the first week 20%, the second week 30%, the
third week 10% etc.
How do I enter this in MSP?

Regards
Kay
 
D

Dale Howard [MVP]

Kay --

Click View - Task Usage. In the timephased grid on the right side of the
page (yellow/white timesheet), manually type the Work for the resource
assigned to that task. Hope this helps.
 