K
Kay
Dear all,
I have one resource, one task.
the resource shall work the first week 20%, the second week 30%, the
third week 10% etc.
How do I enter this in MSP?
Regards
Kay
I have one resource, one task.
the resource shall work the first week 20%, the second week 30%, the
third week 10% etc.
How do I enter this in MSP?
Regards
Kay