One to Many Risks to tasks

S

Steve

Can I link Risk/issues to tasks in different enterprise project plans or only
to the plan that the workspace belongs to ?
 
D

Dale Howard [MVP]

Steve --

You can link a Risk or Issue to tasks in the project associated with the
Project Workspace. You cannot link a Risk or Issue to a task in another
Project Workspace.
 
S

Steve

does that still apply even if they are nested in a Master Program/sub-project
manner?
 