Hi, all
How can I insert an one year task duration in Project (time unit 1y don't
work)?
Thanks
How can I insert an one year task duration in Project (time unit 1y don't
work)?
Thanks
Edward@BR said:Hi, Dale
Ok, this is a solution.
But the question is: why the option at Tools, Options, Edit > View options
for time units in ... ?
It's really don't works? It's a bug?
Thanks
Gérard Ducouret said:Hi Dale, hi Edward,
I think that the "Year" unit was never usable for Duration. It's only
usable for resource salary : for exemple John earns $50,000/year.
Gérard Ducouret
"Dale Howard [MVP]" <dale[dot]howard[at]msprojectexperts[dot]com> a écrit
dans le message de (e-mail address removed)...Edward --
When I attempt to enter a Duration value in years, such as "1y" I get a
warning message and the system does not allow me to enter the desired
Duration value. I would suspect it is a bug, but only Microsoft staff
would know for sure. It doesn't work in Project 2010 either, and I don't
know any workaround. Hope this helps.
Gerard --
Excellent point! Thanks for sharing.
Grard Ducouret said:Hi Dale, hi Edward,
I think that the "Year" unit was never usable for Duration. It's only
usable for resource salary : for exemple John earns $50,000/year.
Grard Ducouret
"Dale Howard [MVP]" <dale[dot]howard[at]msprojectexperts[dot]com> a crit
dans le message de (e-mail address removed)...Edward --
When I attempt to enter a Duration value in years, such as "1y" I get a
warning message and the system does not allow me to enter the desired
Duration value. I would suspect it is a bug, but only Microsoft staff
would know for sure. It doesn't work in Project 2010 either, and I don't
know any workaround. Hope this helps.
Hi, Dale
Ok, this is a solution.
But the question is: why the option at Tools, Options, Edit > View
options
for time units in ... ?
It's really don't works? It's a bug?
Thanks
----------------
Edward
"Dale Howard [MVP]" escreveu:
Edward --
How about entering 52w as the Duration?
Hi, all
How can I insert an one year task duration in Project (time unit 1y
don't
work)?
Thanks