Hi Nicole,
Sorry but PMS Project is all about Projects.
Projects by definition have a start and an end, and all tasks are planned to
have a start and an end date.
Training never stops, but for instance "The 2004 program for Management
Development" does, it has tasks that are linked together, dates top respect,
resources to plan...
Activities with no start and no end cannot be planned in Project.
If you really need to show some, make them for instance "Training through
2005" which has start and en dates.
HTH