A
aljohnso
Problem: When I open a MSProject server file, the start date on one of the
tasks changes instantly, seemingly with cause.
Details: The creator of the file set the constraint on a task to be , "Start
no earlier than" 5/2/05. The constraint on it's parent task is "Start as
soon as possible," with no date set. When she views the file, the task start
date shows correctly as 5/2/05.
When I open the file, the Start date for that task immediately changes to
9/1/05. The constraint remains "Start as soon as possible" with a date of
5/2/05.
The Project start date is 5/2/05.
The (workgroup) resource assigned to the task has no other tasks assigned.
There are no local resources on the resource sheet for this project.
I'm using Office Professional, 2003 (11.1.2004.1707.15) SP1.
I suspect I have some local setting which is causing the date to move out,
but I have no idea what it might be. All suggestions welcome.
Thanks!
tasks changes instantly, seemingly with cause.
Details: The creator of the file set the constraint on a task to be , "Start
no earlier than" 5/2/05. The constraint on it's parent task is "Start as
soon as possible," with no date set. When she views the file, the task start
date shows correctly as 5/2/05.
When I open the file, the Start date for that task immediately changes to
9/1/05. The constraint remains "Start as soon as possible" with a date of
5/2/05.
The Project start date is 5/2/05.
The (workgroup) resource assigned to the task has no other tasks assigned.
There are no local resources on the resource sheet for this project.
I'm using Office Professional, 2003 (11.1.2004.1707.15) SP1.
I suspect I have some local setting which is causing the date to move out,
but I have no idea what it might be. All suggestions welcome.
Thanks!