J
James Dixon
(Second part of Opinions Wanted (1) post).
==========================================
2. Using "ID only" and cutting and pasting tasks to level
So, using this structure:
Milestone 1 V----------------V
Art Staff V----------V
Fred V-------V
Task 1 xxx
Task 2 xxx
Task 3 xxx
Joe V----------V
Task 4 xxxx
Task 5 xx
Task 6 xxxxxx
Tech Staff V----------------V
Jane V----V
Task 7 xx
Task 8 xx
Task 9 xx
Ed V----------------V
Task 10 xxxxxxx
Task 11 xxxx
Task 12 xxxxxxx
we can have full control of what order the work is carried out, simply by
moving the tasks of a person around (cut&paste or drag&drop). E.g. If it
turns out that I want Fred to do Task 3 before Task 1, then I simply drag it
above, and relevel. Again, this would seem to totally negate any concept of
using a WBS?
The reason behind this is to deal with preferential rather than enforced
work order. We still want to use links just for enforced dependencies, but
sometimes we would rather work happens in a certain order, for milestone
delivery purposes, even if there is strictly no need.
Eg, say we're designing a web site.
Website Project
Page 1
Task 1 (design)
Task 4 (script)
Task 9 (artwork)
Task 11 (testing)
Page 2
Task 2 (design)
Task 5 (script)
...
Milestone 1 is Page 1
Milestone 2 is Page 2
Strict dependencies would be:
p1 design -> p1 art
p1 design -> p1 script
p1 script -> p1 test
p1 art -> p1 test
(and the same for page 2).
No dependencies exist between pages 1 and 2, but we want M1 to be before M2,
thus we would want the designer to design Page 1 before Page 2 (let's
pretend it's the same resource, that therefore needs levelling). This is
obviously *extremely* simplified.
Traditionally I have done this by jigging priorities and using the
"Priority, Standard" level order. Is this the right way of doing things?
How else could I ensure that MS Project levels for M1 to be before M2
without resorting to ID levelling?
Thanks again,
James Dixon.
==========================================
2. Using "ID only" and cutting and pasting tasks to level
So, using this structure:
Milestone 1 V----------------V
Art Staff V----------V
Fred V-------V
Task 1 xxx
Task 2 xxx
Task 3 xxx
Joe V----------V
Task 4 xxxx
Task 5 xx
Task 6 xxxxxx
Tech Staff V----------------V
Jane V----V
Task 7 xx
Task 8 xx
Task 9 xx
Ed V----------------V
Task 10 xxxxxxx
Task 11 xxxx
Task 12 xxxxxxx
we can have full control of what order the work is carried out, simply by
moving the tasks of a person around (cut&paste or drag&drop). E.g. If it
turns out that I want Fred to do Task 3 before Task 1, then I simply drag it
above, and relevel. Again, this would seem to totally negate any concept of
using a WBS?
The reason behind this is to deal with preferential rather than enforced
work order. We still want to use links just for enforced dependencies, but
sometimes we would rather work happens in a certain order, for milestone
delivery purposes, even if there is strictly no need.
Eg, say we're designing a web site.
Website Project
Page 1
Task 1 (design)
Task 4 (script)
Task 9 (artwork)
Task 11 (testing)
Page 2
Task 2 (design)
Task 5 (script)
...
Milestone 1 is Page 1
Milestone 2 is Page 2
Strict dependencies would be:
p1 design -> p1 art
p1 design -> p1 script
p1 script -> p1 test
p1 art -> p1 test
(and the same for page 2).
No dependencies exist between pages 1 and 2, but we want M1 to be before M2,
thus we would want the designer to design Page 1 before Page 2 (let's
pretend it's the same resource, that therefore needs levelling). This is
obviously *extremely* simplified.
Traditionally I have done this by jigging priorities and using the
"Priority, Standard" level order. Is this the right way of doing things?
How else could I ensure that MS Project levels for M1 to be before M2
without resorting to ID levelling?
Thanks again,
James Dixon.