A
anovak
Well, I thought I had found a solution for keeping track of
operational items (database backups, customer support, etc.) by just
creating a full list of those categories as Administrative lines and
uncheck the box that displays them all the time (most won't apply to
all). Then just use Timesheets for reporting time on operational
activities and non-work (use My Task for project progress only).
To my dismay, I was unable to add a line to the timesheet from one of
the Administrative items I added. What then is the correct approach
to building buckets for tracking operational activities?
Thanks,
Andy Novak
UNT
operational items (database backups, customer support, etc.) by just
creating a full list of those categories as Administrative lines and
uncheck the box that displays them all the time (most won't apply to
all). Then just use Timesheets for reporting time on operational
activities and non-work (use My Task for project progress only).
To my dismay, I was unable to add a line to the timesheet from one of
the Administrative items I added. What then is the correct approach
to building buckets for tracking operational activities?
Thanks,
Andy Novak
UNT