M
Marcello
Hi,
I've got a question regarding the attached project file (MS Projec
2007). I've added a task and created two resources, one with a max
assignment of 100 % (8 hours per day) and one with a max. assignment o
50 % (4 hours per day).
I added the "work" column in my Gantt view and entered 10 hours of wor
(NOT duration) for the only task in the project and then assigned bot
resources.
When selecting the "resource usage" view I can see that both resource
are allocated equally (each one working 5 hours on the task). So th
Task will be completed in 2 business days.
But as one of the resources can work 100 % (= 8 hours a day) the tas
could be finished earlier (in one business day) by assigning 6 hours t
the first resource and 4 hours to the second resource.
Is there a way to do this automatically (i.e. let ms project optimiz
the resource allocation so that tasks are finished as soon as possibl
even though the workload is not evenly distributed between all assigne
resources)?
I know that I can resolve the issue by manually entering the workin
hours in the resource usage view but some "intelligent" automatism woul
be nice.
Any help would be greatly appreciated!
Kind regards,
Marcell
+-------------------------------------------------------------------
|Filename: Testproject.zip
|Download: http://forums.techarena.in/attachment.php?attachmentid=7396
+-------------------------------------------------------------------
I've got a question regarding the attached project file (MS Projec
2007). I've added a task and created two resources, one with a max
assignment of 100 % (8 hours per day) and one with a max. assignment o
50 % (4 hours per day).
I added the "work" column in my Gantt view and entered 10 hours of wor
(NOT duration) for the only task in the project and then assigned bot
resources.
When selecting the "resource usage" view I can see that both resource
are allocated equally (each one working 5 hours on the task). So th
Task will be completed in 2 business days.
But as one of the resources can work 100 % (= 8 hours a day) the tas
could be finished earlier (in one business day) by assigning 6 hours t
the first resource and 4 hours to the second resource.
Is there a way to do this automatically (i.e. let ms project optimiz
the resource allocation so that tasks are finished as soon as possibl
even though the workload is not evenly distributed between all assigne
resources)?
I know that I can resolve the issue by manually entering the workin
hours in the resource usage view but some "intelligent" automatism woul
be nice.
Any help would be greatly appreciated!
Kind regards,
Marcell
+-------------------------------------------------------------------
|Filename: Testproject.zip
|Download: http://forums.techarena.in/attachment.php?attachmentid=7396
+-------------------------------------------------------------------