K
Klem
Hi ,
I am currently seeting up a project with microsoft Project and I have an
issue with the ressources. The problem is the following. I have a number
limited of ressources: technicians and machines. The purpose is to schedule
tests in my department. Each test needs to respect a logical order between
each tasks but also needs the availability of ressources. For the moment, I
schedule manually the tests and try not to overallocate the ressources (with
the help of the function "level workload"). But I have to schedule many tests
in a limited time and it is a painfull job. I think that I should use
Microsoft Project Server but my boss would like to know if it is worth it to
buy it or not. I think it is. Give me some advices please !!!
I am currently seeting up a project with microsoft Project and I have an
issue with the ressources. The problem is the following. I have a number
limited of ressources: technicians and machines. The purpose is to schedule
tests in my department. Each test needs to respect a logical order between
each tasks but also needs the availability of ressources. For the moment, I
schedule manually the tests and try not to overallocate the ressources (with
the help of the function "level workload"). But I have to schedule many tests
in a limited time and it is a painfull job. I think that I should use
Microsoft Project Server but my boss would like to know if it is worth it to
buy it or not. I think it is. Give me some advices please !!!