J
JR Winder
Hi,
I was recently able to watch a CBT series of videos for MS Project. The
instructor within the videos made some interesting recomendations in regards
to changing some of the default options Project comes with and also the way
in which work/duration for tasks is entered. I'm interested in feedback
from the MVP's of this forum as to if these recomendations make sense or are
even needed.
One of the option chnages was to change the 'Default task type" from 'Fixed
Units' to 'Fixed Work'. He said it was his opinion that MS got this wrong
when they released Project. I've done some reading but haven't really been
able to understand how 'Fixed Work' impacts the project schedule differently
than 'Fixed Units'. Does this recomendation make sense?
The other recomendation he made that I'm confused about is he suggested
adding the 'Work' field column to the Gnatt Chart view and use it rather
than 'Duration' to enter task time estimates. Does this tie into the 'Fixed
Work' task type recomendation above. Is there any benifit to entering a
tasks time into the 'Work' field rather than the 'Duration' field?
Thanks for you time and assistance.
JR
I was recently able to watch a CBT series of videos for MS Project. The
instructor within the videos made some interesting recomendations in regards
to changing some of the default options Project comes with and also the way
in which work/duration for tasks is entered. I'm interested in feedback
from the MVP's of this forum as to if these recomendations make sense or are
even needed.
One of the option chnages was to change the 'Default task type" from 'Fixed
Units' to 'Fixed Work'. He said it was his opinion that MS got this wrong
when they released Project. I've done some reading but haven't really been
able to understand how 'Fixed Work' impacts the project schedule differently
than 'Fixed Units'. Does this recomendation make sense?
The other recomendation he made that I'm confused about is he suggested
adding the 'Work' field column to the Gnatt Chart view and use it rather
than 'Duration' to enter task time estimates. Does this tie into the 'Fixed
Work' task type recomendation above. Is there any benifit to entering a
tasks time into the 'Work' field rather than the 'Duration' field?
Thanks for you time and assistance.
JR