J
JodyJ
What is the order of precedence for calendars?
For example, I have a project calendar that has a non-work day defined
(let's say 7/20). All of my resources have their own calendars defined.
None of them has this day defined as a non-work day. How does MS Project
schedule work in this situation? Is there an order of precedence or does
Project read all calendars and then determine if work can be scheduled?
For example, I have a project calendar that has a non-work day defined
(let's say 7/20). All of my resources have their own calendars defined.
None of them has this day defined as a non-work day. How does MS Project
schedule work in this situation? Is there an order of precedence or does
Project read all calendars and then determine if work can be scheduled?