I'm having a problem with some "orphaned" task reminders that are generating
out of Project Server. These tasks are no longer in the project plans, but
the resource assignments are getting "overdue" notices on them. Is there
something we can look at for getting those cleaned up? The "clean up"
feature of the admin piece is sort of a sledgehammer - you can delete
everything (including actuals) older than date XX/XX/XX, but I don't' want to
risk deleting something I still need - these projects are very much still
active.