Dear experts
My problem related to the fact that there are values at the
At the resource usage view, that I cannot explain.
At the resource usage view, For each user you can see his tasks and his
Other projects and commitments.
When using the load summery resource assignment. you can find information on
time sheets/tasks from other project etc.
At the row of the Other projects and commitments, there are 2 rows (Work and
Rem.A)
This row should aggregate information from its sub rows.
I encountered cases that at the Other projects and commitments, in the Work
fields I can see values with no reasons.
No reasons means that I can see values at the work field at the Other
projects and commitments row level and there is no values in the sub rows for
specific dates.
Does anyone familiar with this problem and know know what to do?
Regards
My problem related to the fact that there are values at the
At the resource usage view, that I cannot explain.
At the resource usage view, For each user you can see his tasks and his
Other projects and commitments.
When using the load summery resource assignment. you can find information on
time sheets/tasks from other project etc.
At the row of the Other projects and commitments, there are 2 rows (Work and
Rem.A)
This row should aggregate information from its sub rows.
I encountered cases that at the Other projects and commitments, in the Work
fields I can see values with no reasons.
No reasons means that I can see values at the work field at the Other
projects and commitments row level and there is no values in the sub rows for
specific dates.
Does anyone familiar with this problem and know know what to do?
Regards