J
JosieMarley
I'm struggling again and could do with some help. I'm using Project 2007 and
use resource levelling. In project 2003 I got adept at working out what I'd
done wrong if my levelling didn't work out the way I wanted (priority levels,
not having all the projects open that a resource was working on etc. etc.).
However with project 2007 all my normal checks aren't picking up why I'm
getting this particular issue.
I have a resource working on a project. We have three other plans in which
all of this resource's tasks have been completed in the past. This shouldn't
have an effect on the levelling so normally I wouldn't bother opening these
projects. However my resource's assignments are shooting way out to January
next year. When I look at the resource usage the "Other projects and
commitments" looks really, really wierd. The Actual Work and the Remaining
Work equal each other and the percentage work complete is 0% both at the top
level and for each of the unopened projects when I unroll!??! In the right
hand side of the screen there is work planned up to the end of January for
the "Summary of Other projects and commitments" (!) but not for each of the
unopened projects.
Going back into the past the Actual Work and Work do match for the unopened
projects, which is correct. The sum of the Actual Work is rolling up into
the "Other projects and commitments" correctly but the Work isn't.
When I open one of these other projects it shows correctly that there is no
work remaining for this resource.
We're using SP1 and our IT services have assured me that uploading the very
latest hotfix (May 8th for project server and whatever date it was for
project) that all the previous post SP1 hotfixes are automatically included.
Any ideas? All four projects were originally on project server 2003 and
project server 2007 was then upgraded about a month ago.
use resource levelling. In project 2003 I got adept at working out what I'd
done wrong if my levelling didn't work out the way I wanted (priority levels,
not having all the projects open that a resource was working on etc. etc.).
However with project 2007 all my normal checks aren't picking up why I'm
getting this particular issue.
I have a resource working on a project. We have three other plans in which
all of this resource's tasks have been completed in the past. This shouldn't
have an effect on the levelling so normally I wouldn't bother opening these
projects. However my resource's assignments are shooting way out to January
next year. When I look at the resource usage the "Other projects and
commitments" looks really, really wierd. The Actual Work and the Remaining
Work equal each other and the percentage work complete is 0% both at the top
level and for each of the unopened projects when I unroll!??! In the right
hand side of the screen there is work planned up to the end of January for
the "Summary of Other projects and commitments" (!) but not for each of the
unopened projects.
Going back into the past the Actual Work and Work do match for the unopened
projects, which is correct. The sum of the Actual Work is rolling up into
the "Other projects and commitments" correctly but the Work isn't.
When I open one of these other projects it shows correctly that there is no
work remaining for this resource.
We're using SP1 and our IT services have assured me that uploading the very
latest hotfix (May 8th for project server and whatever date it was for
project) that all the previous post SP1 hotfixes are automatically included.
Any ideas? All four projects were originally on project server 2003 and
project server 2007 was then upgraded about a month ago.