I have a task with a "must start on" constraint of Monday
6pm and duration of 1 hour. There is one resource
assigned to the task. This resource has been assigned
the "24 hours" calendar. My project plan show the start
date of the task as Monday 6pm, but the finish date is
Tuesday 9am. What am I missing? Why is the finish date
not Monday 7pm?