Outdent cannot be undone.

N

Nick Ville

Hi all,

Let's assume that there are two tasks. Name first as A and second as B. If
we indent B then A becomes a summary task. And we cannot outdent B because
"this option" is not available. We can undo action if file is notsaved. But
if saved no outdent option. In addtion to that behaviour, if B is deleted, A
remains as summary task and cannot be changed to normal.

this behaviour is not as described here in Project 98. Does anyone knows
chages to Project 2003 or is this a by design or known issue?

Thanks,

regards,
Nick.
 
R

Rod Gill

Hi,

If you are using Project 2003 then this is a known bug. Search the
Microsoft.com site for the patch. If you are using an earlier version then
you need to be sorted by ID for outdenting to work.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top