I have just upgraded to Project 2003. I have just come
across a problem while trying to outdent:

If I have:
Stage 1
Task A
Task B
Task C

and want to outdent all the tasks to the same level, I
can only outdent Tasks B, C and D not Task A. The only
way I have found of getting all the tasks back to the
same level is deleting Stage 1, which deletes Task A
also, and then adding the tasks again. In previous
versions I could have just highlighted Tasks A to D and
outdented them all at once, thus making Stage 1 NOT a
Summary task.

Can anyone help?

Thankyou in advance
Judith
 
J

Jan De Messemaeker

Hi,
This is a known bug. There is a KB article on that, but it seems preferrable
to download the whole SP1 which also corrects this.