Outline Code9 not always saved

R

Rui Dias

Hi there!

I'm using Team Foundation Server and Project Server 2007 both with different
purposes.
On PS I manage my project, and in some cases I publish some tasks into TFS
to check-in purpose.
The time is managed with web access, so when I publish into TFS the time is
stored in TFS.
After this I publish into PS and all seems to be OK.

However there is a strange behaviour I don´t understand. When I reopen
project file from PS, all tasks come well configured except two custom
fields (Outline Code9 and Outline Code10 - created when I connect project
file with TFS Project) that in some tasks they have values but in other
tasks they don't have values.
This behaviour is random. Sometimes this happens with some tasks and the
next time it happens with other tasks without apparent logic.

Am I making any sense?
Can someone help me?

Best Regards,
Rui Dias
 