M
Miaplacidus
I have an RFP which outlines a number of reviews, schedule for the reviews,
Major tasks under each review and documents to be provided for Major task.
The Documents are mostly engineering documents.
I entered the tasks in project so that the documents roll up to the Major
tasks, and major tasks rollup to the reviews. The revies roll upt to the
phase and program level.
The RFP also gives a defined WBS structure. This is an engineering WBS such
that tasks roll up to components, components to subsystems, then to the
deliverable system. However the Engineering WBS also has other work like
reilability, safety, logistics that don't logically flow up to a deliverable
item. However, these tasks have documents that are called out in the reviews.
So, after I entered all the tasks reports and reviews that are required, I
opened an outline code field and used it to assign my tasks to the reqired
WBS.
Now I can sort by the Project Generated WBS or the RFP required WBS.
But, when I sort by the RFP required WBS the costs no longer roll up
correctly.
Aside from dismantling all my precedents and undoing the outlining manually,
then sorting by the Required WBS and then redoing the outline and precedents,
how can I change the way the costs roll up?
Major tasks under each review and documents to be provided for Major task.
The Documents are mostly engineering documents.
I entered the tasks in project so that the documents roll up to the Major
tasks, and major tasks rollup to the reviews. The revies roll upt to the
phase and program level.
The RFP also gives a defined WBS structure. This is an engineering WBS such
that tasks roll up to components, components to subsystems, then to the
deliverable system. However the Engineering WBS also has other work like
reilability, safety, logistics that don't logically flow up to a deliverable
item. However, these tasks have documents that are called out in the reviews.
So, after I entered all the tasks reports and reviews that are required, I
opened an outline code field and used it to assign my tasks to the reqired
WBS.
Now I can sort by the Project Generated WBS or the RFP required WBS.
But, when I sort by the RFP required WBS the costs no longer roll up
correctly.
Aside from dismantling all my precedents and undoing the outlining manually,
then sorting by the Required WBS and then redoing the outline and precedents,
how can I change the way the costs roll up?