Outline Level

E

Eán

Is there a way to copy and past the outline level in Microsoft Project?

Many thanks
 
J

JulieS

Hello Eán,

If you mean copy the outline level from one task into/over the
outline level for another task, no. The outline level field is
calculated by Project when you indent or outdent tasks. You can
manually enter a logical value in the field.

However you can copy and paste the outline level value from the
outline level field into a spare field (text or number).

Perhaps if you tell us what you wish to accomplish we can be of more
assistance.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
E

Eán

Hi
Apologies for my vague question, I did mean copy & paste cross projects, but
you have answered my question here - so thank you very much.

Regards,
éan
 