Outline Levels

L

Linnea

Hi,

I am working with MS Project 2000. I have established outline levels. Ie. Level 1 is the Project, Level 2 is the Variance number and then Level 3 I have the Tasks within each variance (numberical number). How do I display these levels in my resource useage sheet? How do I show my levels and the tasks within the established reports or do I need to create a new report? ie. To show the report of who does what when
Any help would be greatly appreciated
Thanks
 
M

Mike Glen

Hi Linnea,

try Insert/Column and select the Task Summary Name field. A for the
reports, these are based on Tables - so create a new table with what you
want and, in Reports, create (or Copy and rename) a new report with that
table.

Next time, try posting on the server newsgroup, as this one is closing down!
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://www.mvps.org/project/.

Mike Glen
Project MVP

Linnea said:
Hi,

I am working with MS Project 2000. I have established outline levels. Ie.
Level 1 is the Project, Level 2 is the Variance number and then Level 3 I
have the Tasks within each variance (numberical number). How do I display
these levels in my resource useage sheet? How do I show my levels and the
tasks within the established reports or do I need to create a new report?
ie. To show the report of who does what when.
 