Outline Number and WBS fields

  • Thread starter John Castle \(again!\)
  • Start date
J

John Castle \(again!\)

Are the above two fields the same in content? If so why
have two fields? Also and I know this is more of an
excel type question, how can I format exported WBS data
to be in numerical ascending order eg 1.9 to come before
1.10 not the other way round!

Rgds

John
 
J

Jan De Messemaeker

Hi John,

Outline number is a Project calculated field
WBS is "tunable" and when you have changed the plan you have to renumber

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 