Hi, All,
I have a problem when update task progress from outlook. when 1st time I
updated a task progress it looks work on the page. However the message on top
right of the window is always "Update for this item have not yet been saved
to Project Web Access" after I pressed <Save to Project Web Access> button.
And no any changes will be presented on to Project_Professional and Projec
Web Access field.
It is even worse that if I tried to work with the same task in Outlook
oncemore, a pop-up message will prompt for reloading add-ins ("Please reload
the project add-in for outlook by clicking trust center on the tools menu.
From there, click Add-Ins..."). By closing this pop-up messge, another error
message shows:
Run time error '380'
Component: UserInterface.Cls
Procedure: ResizeFormFromRes
Error Number: 380
Error source: Forms.Form.1
Error Description: Can not set Width Property. Invalide Property Value.
Enter a value greater than or equal to zero.
I followed instructions to reload add-in several times, it doesn't work. Can
someone tell me: How can I solve this issue?
2- Which form is it mentioned?
3- Can I remove <Time sheet> tab when we open a task from Outlook?
Thanks in advance,
JJin
I have a problem when update task progress from outlook. when 1st time I
updated a task progress it looks work on the page. However the message on top
right of the window is always "Update for this item have not yet been saved
to Project Web Access" after I pressed <Save to Project Web Access> button.
And no any changes will be presented on to Project_Professional and Projec
Web Access field.
It is even worse that if I tried to work with the same task in Outlook
oncemore, a pop-up message will prompt for reloading add-ins ("Please reload
the project add-in for outlook by clicking trust center on the tools menu.
From there, click Add-Ins..."). By closing this pop-up messge, another error
message shows:
Run time error '380'
Component: UserInterface.Cls
Procedure: ResizeFormFromRes
Error Number: 380
Error source: Forms.Form.1
Error Description: Can not set Width Property. Invalide Property Value.
Enter a value greater than or equal to zero.
I followed instructions to reload add-in several times, it doesn't work. Can
someone tell me: How can I solve this issue?
2- Which form is it mentioned?
3- Can I remove <Time sheet> tab when we open a task from Outlook?
Thanks in advance,
JJin