A
Aaron
Hi there. Our company use a shared appointment calendar to schedule the production and delivery of our products. We use a custom form that obviously includes the 'Start' field to determine the delivery date. As we have different stages in manufacturing we would also like some more 'Due Dates'.
For example. If the job is due to be delivered on August 8th, we might want to ensure that 'Assembly' of the product is completed by August 5th. Therefore I would like an Assembly Due Date of August 5th. The way I did this was to create a Field called Assembly-DueDate with type of Date/Time and used a formula in the 'Set the initial value of this field to:' This field will then show the appropriate date that the Assembler must complete this job by. When I give him the schedule I simply replace the Start Date with the Assembly-DueDate.
Up to this point everything works like a charm. Here is my problem. Jobs obviously get moved. Whether it is our fault or the customer just isn't ready we very often need to move the job on the schedule. Because my formula to determine this special date is set as the 'Initial value in the form' it doesn't run again once the job is moved on the schedule. Therefore if the Start Date was August 8th, the Assembly-DueDate is August 5th. If I have to move the job a week to August 15th, the AssemblyDueDate remains at August 5th and not August 12th like I would prefer.
Is there a way I can 'Reload' the form so that the 'Set Initial Value....' formula is run again? If not, does anyone know of a solution to my problem.
thanks.
For example. If the job is due to be delivered on August 8th, we might want to ensure that 'Assembly' of the product is completed by August 5th. Therefore I would like an Assembly Due Date of August 5th. The way I did this was to create a Field called Assembly-DueDate with type of Date/Time and used a formula in the 'Set the initial value of this field to:' This field will then show the appropriate date that the Assembler must complete this job by. When I give him the schedule I simply replace the Start Date with the Assembly-DueDate.
Up to this point everything works like a charm. Here is my problem. Jobs obviously get moved. Whether it is our fault or the customer just isn't ready we very often need to move the job on the schedule. Because my formula to determine this special date is set as the 'Initial value in the form' it doesn't run again once the job is moved on the schedule. Therefore if the Start Date was August 8th, the Assembly-DueDate is August 5th. If I have to move the job a week to August 15th, the AssemblyDueDate remains at August 5th and not August 12th like I would prefer.
Is there a way I can 'Reload' the form so that the 'Set Initial Value....' formula is run again? If not, does anyone know of a solution to my problem.
thanks.