J
Jonathan H
Hello,
I thought I'd cracked all of this, but I think I've found a defect - not
sure there is any other explanation.
Here is the situation:
* I'm using Project Server 2007 with Outlook 2003 with SP 1 applied.
* I don't want to create Timesheets, just use the Tasks functionality
* I do want resources to record when and how much work they have done on a
task, rather than just the percentage complete or the number of hours.
As a result I have changed the Tracking Method to 'Hours of work done per
period'.
In the PWA this works exactly as design, but in the Outlook interface the
'Actual Work' row is greyed out - the User cannot enter any time at all.
Interestingly, the 'Copy from Planned' button is also greyed out.
I have tested the other two Tracking Methods and both work as expected, but
neither gives me the project tracking I'm trying to achieve. I really don't
see the point of work done in the past appearing as if it was carried out in
the future!
Someone please tell me I'm missing something here as otherwise I'm not quite
sure how to proceed. The Resource Availability work that I do in balancing
the resource pool will not work in either other Tracking Method, and I'm
never going to get developers to head off to the PWA when there is already
another Timesheet system in operation.
Help!
Jonathan
I thought I'd cracked all of this, but I think I've found a defect - not
sure there is any other explanation.
Here is the situation:
* I'm using Project Server 2007 with Outlook 2003 with SP 1 applied.
* I don't want to create Timesheets, just use the Tasks functionality
* I do want resources to record when and how much work they have done on a
task, rather than just the percentage complete or the number of hours.
As a result I have changed the Tracking Method to 'Hours of work done per
period'.
In the PWA this works exactly as design, but in the Outlook interface the
'Actual Work' row is greyed out - the User cannot enter any time at all.
Interestingly, the 'Copy from Planned' button is also greyed out.
I have tested the other two Tracking Methods and both work as expected, but
neither gives me the project tracking I'm trying to achieve. I really don't
see the point of work done in the past appearing as if it was carried out in
the future!
Someone please tell me I'm missing something here as otherwise I'm not quite
sure how to proceed. The Resource Availability work that I do in balancing
the resource pool will not work in either other Tracking Method, and I'm
never going to get developers to head off to the PWA when there is already
another Timesheet system in operation.
Help!
Jonathan