D
DF
Hi, All !
Project manager (PM) in my company want to get % complete of all SUMMARY
project tasks in Outlook (every morning sync). For integation with Outlook i
set resource (PM) to all summary tasks. Importing tasks in Outlook is
correct. But after tasks in Outlook is updated, % complete of summary tasks
steel leave 0.
I foud out, that % of task complete in PWA is grow as subtasks completed,
but % of work complete leave 0.
Is there any way to pass in Outlook % of summary task complete correctly?
MS Projetc Server 2007 Sp1, Outlook 2007
Project manager (PM) in my company want to get % complete of all SUMMARY
project tasks in Outlook (every morning sync). For integation with Outlook i
set resource (PM) to all summary tasks. Importing tasks in Outlook is
correct. But after tasks in Outlook is updated, % complete of summary tasks
steel leave 0.
I foud out, that % of task complete in PWA is grow as subtasks completed,
but % of work complete leave 0.
Is there any way to pass in Outlook % of summary task complete correctly?
MS Projetc Server 2007 Sp1, Outlook 2007