Outlook tasks not importing all

M

mrrrl

Running Project Server 2007 and Outloop 2007. We recently installed the
outlook add-in. When we try to import new assigments into Outlook we only get
a partial list of tasks. Seems to be just new tasks added recently. No tasks
from older but still valid projects. Should it not import every task
assignement to the resource?
Any ideas?
 
D

Dale Howard [MVP]

mrrrl --

No, you have to configure the Project Server add-in in Outlook by going to
Tools - Options - Project Web Access. You will see that the default
settings only import the next two weeks worth of tasks. You need to specify
several other settings as well in this dialog. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top