Not sure if anyone can help with this or not but it has been bugging me.
When you import tasks from project into MS Outlook Calendar it imports it for
the entire day and the entrie duration. If I have a task that runs 5 days
and the resource works that task maybe 10% during those five days it imports
the task for the entire day all five days. By doing this the reminder comes
up everyday and reminds you that this is due but actually it isn't due until
the fifth day.
Does anyone know how to import tasks with durations of more than a day and
less than 100% each day and not make it smearit for 8 hours everyday. It
really isn't a big deal but just bothering me. It makes the tool non usable
in this manner.
Thanks!
When you import tasks from project into MS Outlook Calendar it imports it for
the entire day and the entrie duration. If I have a task that runs 5 days
and the resource works that task maybe 10% during those five days it imports
the task for the entire day all five days. By doing this the reminder comes
up everyday and reminds you that this is due but actually it isn't due until
the fifth day.
Does anyone know how to import tasks with durations of more than a day and
less than 100% each day and not make it smearit for 8 hours everyday. It
really isn't a big deal but just bothering me. It makes the tool non usable
in this manner.
Thanks!