Output Rate Library

A

Andrew

I have an output rate library, which I use to calculate the duration of each
activity: measure x rate / men I currently use Access to do all this for me -
works very well and I am happy with it. However, I have just joined a company
where all this information has to be stored within the programme.This means
me doing it once in Access then transferring the information into Notes. I
understand that I can add columns in for the measure, rate & men and that I
can use a further column with a formula to calculate the manhours etc, but is
there any way of storing the output library so that I can select an output
via a dropdown box?

Andrew
 
A

Andrew

Doh!

Ive just discovered "Value List"

Sorry - I will amend my question - can I get the description from my value
list to show in any way as to how I worked out my duration ie 100m2 Blockwork
x 1.0 / 2 men = 50 man hours

Andrew
 
J

John

Andrew said:
I have an output rate library, which I use to calculate the duration of each
activity: measure x rate / men I currently use Access to do all this for me -
works very well and I am happy with it. However, I have just joined a company
where all this information has to be stored within the programme.This means
me doing it once in Access then transferring the information into Notes. I
understand that I can add columns in for the measure, rate & men and that I
can use a further column with a formula to calculate the manhours etc, but is
there any way of storing the output library so that I can select an output
via a dropdown box?

Andrew

Andrew,
I see no mention of Microsoft Project. Although what you appear to be
doing could be done by Project, if you are not or do not plan on using
Project, I suggest you post to a more appropriate newsgroup. This
newsgroup is dedicated to questions/issues about Microsoft Project, a
planning and scheduling application.

John
Project MVP
 
A

Andrew

John

When I mentioned the programme as oppose to Program, I assumed that everyone
would know that I was talking about MSP, and the fact that I posted in the
Discussions in Microsoft Project General Questions might have given the game
away? Sorry for any misunderstanding from the way my question has been
phrased - the second question is still there regarding the way I can show the
working out, as I have now discovered the Value List, any help would be
appreciated, as at the moment I am writing in everything by hand in notes.

Andrew
 
J

John

Andrew said:
Doh!

Ive just discovered "Value List"

Sorry - I will amend my question - can I get the description from my value
list to show in any way as to how I worked out my duration ie 100m2 Blockwork
x 1.0 / 2 men = 50 man hours

Andrew

Andrew,
Just for your reference we do get a fair number of queries that have
nothing to do with MS Project. If a question doesn't look or smell like
MS Project, we try to direct the poster to a more appropriate newsgroup.

OK, so you are using Project but you'll have to help me out here a
little. I'm having trouble understanding your "formula". Duration is
measured in time. Your "measure" seems to be in square meters (I assume
that's what 100m2 means). What is the dimension on your "rate"? It seems
like it would have to be: man squared hours per meter squared to give an
end result of man hours.

Once the formula is clarified, what exactly are you trying to do? You
mentioned something about a value list. What is in your value list?

The bottom line, what is your end goal?

John
Project MVP
 
V

vanita

Hi Andrew

The method that I have seen normally being followed, is that do this
exercise in Excel and then final manhours calculation could be imported to a
Text column in MSP through copy/paste and linked. So that any changes in
Excel make required changes in MSP column.

Alternatively add 3 Text columns with appropriate titles to show 'measure',
'rate' and 'no. of men' working for each activity. Then have another Text
column with the title 'manhours' as required and customised with a formula
using data from the first 3 text columns inserted. All these columns could be
shown in any report as required by you.

I am little unsure about the formula given by you. But whatever formula you
use, this method could be adopted.

I hope it helps.
Vanita
 
A

Andrew

John I get what you are saying and I apologise for any misunderstanding. To
the question - I will start from the begining

At the moment I use Access to store my database of output rates, it produces
a report telling me the duration, no. men etc.. This software works well and
I have used it for over 5 years. The company I now work for require that we
put all this information in notes so the information stays with the project.
This would mean working the calculations out in access then retyping the
result in MSP notes - a little bit clumsy!, or typing the whole thing in
notes and using a calculator (which is what I am doing at the present - very
time consuming). The formula was just an example, but would be similar to
100m2 x 0.9 (rate equals 0.9M2@hour@man) = man hours/8 = man days/men =
gang/duration the formula is not the issue as it works for me. I have noticed
that in customising Fields there is the facility for a Value list allowing a
dropdown box if you add some information ie rates and a description and you
add the column to your view. I also get that you can add false columns to
work out the duration by adding simple formulas. The end goal if you like is
I would like to use the Value list facility (I run a planning team and would
like to have all my planners using the same set of rates in an easy method)
but would like to see the description of the rate , as only the value is put
in the column and I do not know how to access the description, and be able to
import into the Value list either from Access or Excell as I have over 700
rate items, otherwise lots of typing!!. Failing this is there a way of
accessing either Access or Excell from within MSP and importing information
into notes. With the aim of streamlining the process. I am however open to
any other suggestions as to how this can be achieved.

Many regards

Andrew
 
J

John

Andrew said:
John I get what you are saying and I apologise for any misunderstanding. To
the question - I will start from the begining

At the moment I use Access to store my database of output rates, it produces
a report telling me the duration, no. men etc.. This software works well and
I have used it for over 5 years. The company I now work for require that we
put all this information in notes so the information stays with the project.
This would mean working the calculations out in access then retyping the
result in MSP notes - a little bit clumsy!, or typing the whole thing in
notes and using a calculator (which is what I am doing at the present - very
time consuming). The formula was just an example, but would be similar to
100m2 x 0.9 (rate equals 0.9M2@hour@man) = man hours/8 = man days/men =
gang/duration the formula is not the issue as it works for me. I have noticed
that in customising Fields there is the facility for a Value list allowing a
dropdown box if you add some information ie rates and a description and you
add the column to your view. I also get that you can add false columns to
work out the duration by adding simple formulas. The end goal if you like is
I would like to use the Value list facility (I run a planning team and would
like to have all my planners using the same set of rates in an easy method)
but would like to see the description of the rate , as only the value is put
in the column and I do not know how to access the description, and be able to
import into the Value list either from Access or Excell as I have over 700
rate items, otherwise lots of typing!!. Failing this is there a way of
accessing either Access or Excell from within MSP and importing information
into notes. With the aim of streamlining the process. I am however open to
any other suggestions as to how this can be achieved.

Many regards

Andrew

Andrew,
I still don't understand your formula - the "m2" and "M2" are a mystery.
Unfortunately unless I, (or someone else who responds), can understand
it, our help will be limited. Nonetheless, here are some things that
will help.

First a little explanation of how Project works is in order. Man hours
is NOT duration, it is work effort. Duration is the time span during
which a task is planned to be worked on. Work is the effort put forth by
one or more resources to accomplish the task. If a single resource is
working full time on a task then the Duration and Work fields will be
equal. Normally however, a single resource will not work full time on a
given task or multiple resources will work on a task. For example, let's
say a single resource works half time on a task for a week. The task
duration is 5 days but the work effort is 20 hours. Similarly, if two
resources work full time on a task for 5 days, the duration is still 5
days but the work effort is 80 hours. You need to take that into account
when you apply your formula.

Second, the description IS displayed when the value list is activated in
the view. That means that the user does see the rate description when
selecting a particular rate for that task. Project does not display the
description once a value is selected because that's not what a value
list is for.

Third, because the dimension of your "rate" is still unclear I don't
know whether it should be something related to a task or to a resource.
If using a value list is indeed the best approach, (and I don't know
that it is), a task value list is different from a resource value list.
For a better understanding of this concept, go to our MVP website at,
http://www.mvps.org/project/faqs.htm, and take a look at FAQ 51 - Data
Types: Task, Resource and Assignment.

Fourth, is is possible to import Access or Excel data into Project? Yes.
However, again without understanding your variables the exact import
process is undefined. The most foolproof method of import is via a VBA
macro or possibly an import map but for a one-shot import, VBA is
probably overkill. I assume that once you get your data into Project,
you won't need to do further imports. If the data is straightforward,
even a simple copy and paste may be appropriate although putting that
data into the Notes field is most likely not what you need to do. The
Notes field in Project is strictly for reference information for tasks
or resources and is not intended in any way, shape or form to be an
"active" part of the schedule plan.

So you see, I still have a lot of questions. I see that Vanita also
responded and she to is unsure of your "formula". However, maybe her
suggested straightforward approach to using spare fields is of benefit.
(By the way, spare fields are not "false" columns, they are real adjunct
fields for tasks, resources and assignments).

Hope this helps.

John
Project MVP
 
A

Andrew

John

Thankyou for your patience. I think that we may be looking at this from
totally different perspectives. Let me clarify the formula first. I have to
build 100 squared metres of 140mm block (100m2), I have a rate (a
predetermined construction rate)that says 1 man can build 1m2 in 1hr. So the
formula would look like:
100x1=100 man hours/8 (hours in a day) = 12.5 days I would allocate 3
bricklayers to this task, 12.5/3 = 4.1 gang days, I would then round up to 5
and have 1 day as contingency, therefore the formula would look like:
((100x1)/8)/3. The main point I was trying to make is that the formula works
fine as I use it all the time and I know how to use additional columns as
Vanita suggested, what I wanted was a wasy to reproduce our company policy as
to how we illustrate the calculations. I also understand your comments
regarding notes. We use notes for making notes, for example in the brickwork
activity notes I would enter:

"100m2 measured 140mm block pointed both sides 100x1(rate)= 100 manhours/8 =
12.5 days/3 men = 4.1 gang days round up to 5 = 1 day contingency."

Then when I come to explain my programme I would refer to the entry as to
how I came to 5 days duration. As regards the drop down box, yes I see the
description, but as in access is there a way of showing the description in
another column, so I can see what the rate (value) relates to. As for
manhours and durations etc. We do not use resources interactively, I would
add the duration manually in days, tick the scheduling ignores resource
calendars, and add the resources. We do not level out resources or allow them
to change the duration, the resource level is an estimate by me and we
subcontract our work out and so the resource level is a guide only. I thought
that it would be useful for my department to have a set of construction rates
set in a drop down box kept within MSP, so that we are all working from the
same information, bearing in mind that our company manual dictates that we
write the information in the notes section.

I guess what I am after is some way of having the drop down box, some
columns which will work out the duration, and then some way of putting all
that into notes including the rate description. There, after that we will
look at the middle east.

Many regards

Andrew
 
J

John

Andrew said:
John

Thankyou for your patience. I think that we may be looking at this from
totally different perspectives. Let me clarify the formula first. I have to
build 100 squared metres of 140mm block (100m2), I have a rate (a
predetermined construction rate)that says 1 man can build 1m2 in 1hr. So the
formula would look like:
100x1=100 man hours/8 (hours in a day) = 12.5 days I would allocate 3
bricklayers to this task, 12.5/3 = 4.1 gang days, I would then round up to 5
and have 1 day as contingency, therefore the formula would look like:
((100x1)/8)/3. The main point I was trying to make is that the formula works
fine as I use it all the time and I know how to use additional columns as
Vanita suggested, what I wanted was a wasy to reproduce our company policy as
to how we illustrate the calculations. I also understand your comments
regarding notes. We use notes for making notes, for example in the brickwork
activity notes I would enter:

"100m2 measured 140mm block pointed both sides 100x1(rate)= 100 manhours/8 =
12.5 days/3 men = 4.1 gang days round up to 5 = 1 day contingency."

Then when I come to explain my programme I would refer to the entry as to
how I came to 5 days duration. As regards the drop down box, yes I see the
description, but as in access is there a way of showing the description in
another column, so I can see what the rate (value) relates to. As for
manhours and durations etc. We do not use resources interactively, I would
add the duration manually in days, tick the scheduling ignores resource
calendars, and add the resources. We do not level out resources or allow them
to change the duration, the resource level is an estimate by me and we
subcontract our work out and so the resource level is a guide only. I thought
that it would be useful for my department to have a set of construction rates
set in a drop down box kept within MSP, so that we are all working from the
same information, bearing in mind that our company manual dictates that we
write the information in the notes section.

I guess what I am after is some way of having the drop down box, some
columns which will work out the duration, and then some way of putting all
that into notes including the rate description. There, after that we will
look at the middle east.

Many regards

Andrew

Andrew,
Question, why are you using Project at all? It sounds like you are doing
a spreadsheet type calculation with human estimates for scheduling dates
and times. That pretty much defeats the reason for using Project. I
think you would be better off sticking with Access or perhaps Excel.

For your reference, checking the box to ignore resource calendars isn't
doing what you think. Project calculates a schedule based on the Project
working day calendar. That is the default but each task can have it's
own working calendar which overrides the Project calendar. Further, each
resource assigned to the task can have their own unique calendar, (e.g.
vacation, multiple project commitments, etc.) which overrides the task
calendar. Checking the box to ignore resource calendars simply tells the
Project scheduling engine to schedule per the task or default Project
working day calendar - it does NOT "disconnect" resources that are
assigned to the task.

If you are adding resources, (i.e. assigning them such that their names
appear in the Resource Names column in the Gantt Chart view), they are
in fact working the task interactively. The only way they won't work
interactively is if you simply "add" resources by listing their names in
a spare column, (e.g. Text1), for each task (i.e. don't assign them).

Sure, we could probably set you up with formulas in customized fields
and/or some VBA to dump the info into the Notes field but I really think
you should seriously consider sticking with Access or Excel. I just
don't see a valid reason for using Project in this situation.

Maybe it's time to look at the Middle East now.

John
Project MVP
 
A

Andrew

John

Thankyou for all your efforts, Ill go and get my tent and passport

Regards

Andrew
 
J

John

Andrew said:
John

Thankyou for all your efforts, Ill go and get my tent and passport

Regards

Andrew
Andrew,
You're welcome.

One final comment. Occasionally I run into users who only want to use
Project for its "pretty" Gantt Chart capabilities or simply don't
understand that Project is a complex planning and scheduling
application. I try to explain the proper use of the application.
Sometimes they understand and find a more appropriate application or
sometimes they want to go ahead and use Project anyway in a non-standard
way. Generally the latter either leads to near total frustration or
willingness to engage, (for compensation), the services of someone
knowledgeable with Project to make it do what they need. Unless I
totally missed something, you and the company you work for appear be
trying to use Project in a non-standard way. That's why I suggested
sticking with other applications.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top