S
STEVO
Hi all,
Wondering if anyone can shed some light for me an an annoying issue
which has been troubling me for days now. I am getting resources
highlighted in red, emphasising an over allocation. But on looking
into the allocation of task, these resources have only for example 4
hours work in one day, yet it is stating that this is an
overallocation.
I have checked the calendar assigned to the resource and it is correct,
For example I have .4 days work assigned to me this coming monday, my
calendar is set to 9.30 - 6, yet it is showing me as overallocated for
this day.
Grateful for any assistance.
Kindest Regards
Steve
Wondering if anyone can shed some light for me an an annoying issue
which has been troubling me for days now. I am getting resources
highlighted in red, emphasising an over allocation. But on looking
into the allocation of task, these resources have only for example 4
hours work in one day, yet it is stating that this is an
overallocation.
I have checked the calendar assigned to the resource and it is correct,
For example I have .4 days work assigned to me this coming monday, my
calendar is set to 9.30 - 6, yet it is showing me as overallocated for
this day.
Grateful for any assistance.
Kindest Regards
Steve