J
jhalterm
How do I open up all MS Projects that are associated with the resource that
is over allocated and the day in which he is over allocated. I can't figure
out how to do that without having to really do a lot of work. I can open
each project one by one but this resource has over 20 projects assigned to
him in the next month.
Thanks
is over allocated and the day in which he is over allocated. I can't figure
out how to do that without having to really do a lot of work. I can open
each project one by one but this resource has over 20 projects assigned to
him in the next month.
Thanks