S
SSDSCA
I am probably overthinking this and making it more complicated than it really
is and now have myself really confused. I have a sheet to track project costs
by the day that is fixed at 47 rows, however, the number of colums is
dependent on the job length. I would like to repeat columns A thru H on each
sheet printed out and have the sheets print out 7 days per sheet (2 columns
required for each day) with the code being able to identify the last day
entered and print out the required number of sheets. ie - if the job is 11
days long it would print out 2 sheets, one with 7 days and the second with 4
days with entires and the remaining columns would be printed, however there
would be no entries in these colums.
is and now have myself really confused. I have a sheet to track project costs
by the day that is fixed at 47 rows, however, the number of colums is
dependent on the job length. I would like to repeat columns A thru H on each
sheet printed out and have the sheets print out 7 days per sheet (2 columns
required for each day) with the code being able to identify the last day
entered and print out the required number of sheets. ie - if the job is 11
days long it would print out 2 sheets, one with 7 days and the second with 4
days with entires and the remaining columns would be printed, however there
would be no entries in these colums.