Over taime allocation for Task

L

Lorin

If a task is allocated 10 hours for completion, has taken 15 hours and is
still only 80% complete, how do I report the overage without Project erroring
or changing the percentage to 100%?
 
V

vanita

Hi
Open Gantt chart view and Table > Tracking.

In this table for the task, input data about:
1. Actual Start
2. Actual duration (i.e 15 hrs)
3. Remaining duration (As manager your judgement that how much more time
would be required)
4. '% complete' would automatically be calculated as % of 'Actual duration'
with respect to (Actual + Remaining duration), as % complete is based on
duration.
5. If '% complete' is not 80% and you need to show that quantity wise 80% is
done, input it yourself in 'Physical % complete' cell.

I hope it helps.
Vanita
 
S

Steve House

Vanita and Trevor gave you good answers, just a note of followup. Be
careful with the concepts of "% Complete" and IMHO you should never ask a
resource for such a number - they probably don't have a clue what you're
really asking them. There are really three different percentages and
they're not equivalent, you can't mix and match them. There's "% Complete"
which refers strictly to duration - at 8 days into a task that lasts 10 days
you're 80% complete even if you haven't achieved a darned thing. There's "%
Work Complete" which refers to man-hours expended versus man-hours required.
And then there's "Physical % Complete" which is a usually subjective
estimate of the % of the required deliverable that has been created.

How could % Complete and % Work Complete be different? I'm painting a room.
Mon I do an hour of a first primer coat and let it dry overnight. Tue I do
a second primer, also taking and hour. Wed I do the first colour coat,
takes an hour. Thu I do the second colour coat, taking an hour. Then on
Fri I spend all day doing all the detail work and cleanup. The task
duration is 5 days. The work is 12 man-hours. It's Thu at 4pm and
everything is on schedule. I've crossed over 32 hours of the 40 required,
we're 80% complete. We've done 4 out of the total 12 hours work required -
we're at 33% Work Complete. And we look around the room and only 2 walls
have the final coat of paint. We're 50% physical complete. Always compare
apples to apples.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top