Why oh why does my resource usage view show a resource to
be overallocated with only 5 hours of tasks on a specific
day when the resource is available 8 hours that day?

At one point I thought it could be that they were both
scheduled at the same time that day....but I don't see
where a time is indicated for either of them.

Many TIA,

CB
 
J

Jan De Messemaeker

Hi Catherine,

There is a very nice explanation of this on www.mvps.org/project/faqs
Faq 34 Overallocation occurring in less than one day.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 