We're just getting into looking at resource allocations. We are using the
2007 web access resource center views, and they work well. At least we
understand them. Project Pro has a overallocated resource report. Here's my
problem. When we run the overallocated resource report, the results vary by
PM. As an example: I ran the report with project A open. My associate runs
the same report using project A. The results are different. I get the
resource overallocations including other projects, my associate does not. We
are both set up as administrators. It must have something to do with
ownership, at either a task or project level. I even had one PM tell it was
based on what plan(s) they had open at the time, but I haven't a chance to
confirm this one yet. Can someone, tell me the secret? I can't seem to find
in any documentation.
2007 web access resource center views, and they work well. At least we
understand them. Project Pro has a overallocated resource report. Here's my
problem. When we run the overallocated resource report, the results vary by
PM. As an example: I ran the report with project A open. My associate runs
the same report using project A. The results are different. I get the
resource overallocations including other projects, my associate does not. We
are both set up as administrators. It must have something to do with
ownership, at either a task or project level. I even had one PM tell it was
based on what plan(s) they had open at the time, but I haven't a chance to
confirm this one yet. Can someone, tell me the secret? I can't seem to find
in any documentation.