K. Bolton --
A resource overallocation occurs when a resource is schedule for more work
than they are available to perform in any time period, including as little
as a 15-minute time period. To determine where your resource
overallocations are occurring in your project plan, apply the Resource Usage
view, examine the overallocated resources and the time periods in which the
overallocations are occurring. You can also zoom in to smaller time periods
to see overallocations that occur in less than a full working day time
period. Hope this helps.
K. Bolton said:
The Resource Usage Sheets are showing resources as overallocated at 20-30
hours per week when the resource's calendar is showing them available for 40
hours per week. What is causing this.