G
Gilles
I have created 2 tasks:
One lasts 6 hours on day 1
One lasts 2 days, day1 and day 2
For the first one I have assigned 2 ressources: A & B
I have also assigned B to the second task.
Rightly, project told me Ressource B was over allocated.
Going in "ressouce usage screen", I have kept A assigned 6 hours to the
first task and then assigned him 2 hours on second task during the first day,
and 8 hours on the second day. (his working calendar specifies 8 hours per
day working time for all days).
Project therefor show me in this ressource sheet that there is an 8 hour
assignement only for the first day for A, but still shows this day in red, as
if overallocated.
If I choose to display overallocation field (still in Ressource usage view),
project shows 0.
I I change view to Ressouce Graph, A is overallocated.
What did I do wrong and how to correct?
Even more confusing for me if that in the Ressource graph sheet, it shows an
overallocation of 25%, so 2 hours, which does not even correspond to the
original overallocation (6 hours + 8 hours=14 hours or 175%).
One lasts 6 hours on day 1
One lasts 2 days, day1 and day 2
For the first one I have assigned 2 ressources: A & B
I have also assigned B to the second task.
Rightly, project told me Ressource B was over allocated.
Going in "ressouce usage screen", I have kept A assigned 6 hours to the
first task and then assigned him 2 hours on second task during the first day,
and 8 hours on the second day. (his working calendar specifies 8 hours per
day working time for all days).
Project therefor show me in this ressource sheet that there is an 8 hour
assignement only for the first day for A, but still shows this day in red, as
if overallocated.
If I choose to display overallocation field (still in Ressource usage view),
project shows 0.
I I change view to Ressouce Graph, A is overallocated.
What did I do wrong and how to correct?
Even more confusing for me if that in the Ressource graph sheet, it shows an
overallocation of 25%, so 2 hours, which does not even correspond to the
original overallocation (6 hours + 8 hours=14 hours or 175%).