K
Ken
I have built a consolidated project by inserting 8
subordinate projects. I have levelled resources minute
to minute. Every time I make even a superficial change I
get about 30 dialogue boxes saying "This overallocation
cannot be resolved" etc. Makes sense since we're
shuffling so many project tasks.
My problem is I'm sick of clicking "Skip All" about
twenty times for every change I make. Is there any way
to set a default where Project will automatically "Skip
All" and leave me alone? I just want to get on with
my work and not feel like a monkey clicking my mouse all
day. Thanks for any solution you have to this!
Ken
subordinate projects. I have levelled resources minute
to minute. Every time I make even a superficial change I
get about 30 dialogue boxes saying "This overallocation
cannot be resolved" etc. Makes sense since we're
shuffling so many project tasks.
My problem is I'm sick of clicking "Skip All" about
twenty times for every change I make. Is there any way
to set a default where Project will automatically "Skip
All" and leave me alone? I just want to get on with
my work and not feel like a monkey clicking my mouse all
day. Thanks for any solution you have to this!
Ken