[PS 2007] Hi everyone.
We're using the Enterprise Resource pool, where resources are assigned to
multiple projects.
The problem is this: In several cases, the "Resource Usage" view is showing
overallocation for Resources with a load of work less than 8 hours (which is
their Capacity). I can see the "Other Project and Commitments" line but the
total ammount of hours per day is less than 8 hours and I don't know why is
showing overallocation.
I've checked the "Resource Availabiliy" option in PWA (included the Proposed
bookings) and nothing changes: Same hours of work as seen in Project.
Can anyone tell me why is this happening. This is a link for a screenshot:
http://www.flickr.com/photos/29780143@N02/3330274635/
Thanks for your help.
We're using the Enterprise Resource pool, where resources are assigned to
multiple projects.
The problem is this: In several cases, the "Resource Usage" view is showing
overallocation for Resources with a load of work less than 8 hours (which is
their Capacity). I can see the "Other Project and Commitments" line but the
total ammount of hours per day is less than 8 hours and I don't know why is
showing overallocation.
I've checked the "Resource Availabiliy" option in PWA (included the Proposed
bookings) and nothing changes: Same hours of work as seen in Project.
Can anyone tell me why is this happening. This is a link for a screenshot:
http://www.flickr.com/photos/29780143@N02/3330274635/
Thanks for your help.