Overallocation Inconsistencies in "Resource Usage" View

  • Thread starter Sebastian Cordoba
  • Start date
S

Sebastian Cordoba

[PS 2007] Hi everyone.

We're using the Enterprise Resource pool, where resources are assigned to
multiple projects.

The problem is this: In several cases, the "Resource Usage" view is showing
overallocation for Resources with a load of work less than 8 hours (which is
their Capacity). I can see the "Other Project and Commitments" line but the
total ammount of hours per day is less than 8 hours and I don't know why is
showing overallocation.

I've checked the "Resource Availabiliy" option in PWA (included the Proposed
bookings) and nothing changes: Same hours of work as seen in Project.

Can anyone tell me why is this happening. This is a link for a screenshot:
http://www.flickr.com/photos/29780143@N02/3330274635/

Thanks for your help.
 
S

Sebastian Cordoba

Thank you Jan.

You're right. In the Resource Usage view I applied a Zoom In and then I
realized that both task were starting at the same time (hour-minutes) and the
max capacity for every 15 minute period (which is 0,25 hrs) was surpassed.

Thanks again.
 