J
John_JXL
I am using MSP2003 and often see an issue in resource usage view where (on a
day-by-day basis or even week-by-week) a resource/task is highlighted as
overallocated at that level even though it is not.
I have read previous posts which explain that MS treats any overallocation
against every 60s period and that the recommended fix is to manually edit the
working hours on hour-by-hour basis.
However is there any way to change the setting such that MSP only flags
overallocations on a day-by-day basis (as any smaller time period is not
really relevant to me)? It is quite fiddly and time-consuming to manually
correct overallocations when they do occur even though I am only really
concerned with the day-by-day view.
Does MSP2007 offer any solutions in this area compared with '03?
day-by-day basis or even week-by-week) a resource/task is highlighted as
overallocated at that level even though it is not.
I have read previous posts which explain that MS treats any overallocation
against every 60s period and that the recommended fix is to manually edit the
working hours on hour-by-hour basis.
However is there any way to change the setting such that MSP only flags
overallocations on a day-by-day basis (as any smaller time period is not
really relevant to me)? It is quite fiddly and time-consuming to manually
correct overallocations when they do occur even though I am only really
concerned with the day-by-day view.
Does MSP2007 offer any solutions in this area compared with '03?