T
Tammy
If I add two tasks to occur on the same date (fixed
Duration or fixed units), and I change the work to be one
hour each, it is still saying that I'm at 200%
allocation. It seems to ignore my Work (2 hrs total) and
use Units (100%) so I'm at 200% allocation. I don't
understand how to force it to recognize Work without
playing around with units, duration and work an excess
amount. Shouldn't units be recalculated when I change the
other two fields?
Duration or fixed units), and I change the work to be one
hour each, it is still saying that I'm at 200%
allocation. It seems to ignore my Work (2 hrs total) and
use Units (100%) so I'm at 200% allocation. I don't
understand how to force it to recognize Work without
playing around with units, duration and work an excess
amount. Shouldn't units be recalculated when I change the
other two fields?