R
Rae
Hi ProjectExperts,
I am running four projects concurrently from a master.
I have two resourses showing overallocation.
The first resource is only required in one project (which is 90% completed).
He has one task left worth 1 hours work.
His calendar has plenty of time and this is the last task (not overlapping
any other)
The resource file is showing him at 400% peak. eventhough all of his other
tasks are complete.
Another thing that is strange about this project is the dates have past but
the product is not showing as behind schedule. (Track date is set correctly.)
Any help is appreciated,
I am running four projects concurrently from a master.
I have two resourses showing overallocation.
The first resource is only required in one project (which is 90% completed).
He has one task left worth 1 hours work.
His calendar has plenty of time and this is the last task (not overlapping
any other)
The resource file is showing him at 400% peak. eventhough all of his other
tasks are complete.
Another thing that is strange about this project is the dates have past but
the product is not showing as behind schedule. (Track date is set correctly.)
Any help is appreciated,