C
Conrad Santiago
We have an on-going problem. We have some production resources set at 75% Max Units. We do this because they are project leads and they have duties that arise on projects that are not easily scheduled. While they are scheduled to work on one project, they may be called away to do a QC review or confirm info on another project. For an 8 hour day, set at 75%, they are free to spend two hours a day on such lead duties
The problem is they don't always spend two hours a day on lead duties, so they end up spending 8 hours on a task in one day. Meanwhile, the gantt chart still shows them on a 6-hour day rate to complete the task. Our managers do update these tasks daily asking "How much more time do you need on this task?". When there is only one or two days left on a task, it is easy for the resource to gauge how might more time is needed. However, in the early going on a lengthy task, it is difficult to gauge, resulting in more hours be spent on a task. As the end of the task approaches, the resource is either cut short on allotted time or goes over budget
Where are we going wrong with this approach
Any advice is appreciated
--Conrad Santiago
The problem is they don't always spend two hours a day on lead duties, so they end up spending 8 hours on a task in one day. Meanwhile, the gantt chart still shows them on a 6-hour day rate to complete the task. Our managers do update these tasks daily asking "How much more time do you need on this task?". When there is only one or two days left on a task, it is easy for the resource to gauge how might more time is needed. However, in the early going on a lengthy task, it is difficult to gauge, resulting in more hours be spent on a task. As the end of the task approaches, the resource is either cut short on allotted time or goes over budget
Where are we going wrong with this approach
Any advice is appreciated
--Conrad Santiago