Hi djc,
Welcome to this Microsoft Project newsgroup
An overflow task is one where there's no space left to show it in the
calendar, and Project has no option other than printing it on wanother page.
You can increase the space available in each week by moving your cursor to
the dividing line between any two weeks and dragging downwards. You could
also reduce the height of each row by making fonts smaller. You can also
try Format/Layout... and select to attempt to fit as many tasks as possible.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials