Dave,
Let me help you out here. There are two, (and possibly more), ways to
express progress in Project. The most common way is via percent complete
which is duration based and is used to display the progress line on
Gantt bars. The second is to look at percent work complete. When you
first mentioned progress I immediately focused on the standard percent
complete method. Adding a resource, labor or non-labor to a summary line
has no impact on this measurement and that's where we weren't clicking
at all. You apparently were thinking in terms of percent work complete.
A material resource on a summary line will not affect this parameter
because there is no work associated with a material resource. On the
other hand, for a labor resource, assigning it to a summary line will of
course directly affect the percent work complete parameter because work
is involved.
I trust this now puts us on the same page and helps clarify things for
anyone else who has been following this thread.
John
Project MVP
Good explanation, John. Sometimes I think I've been doing this too
long! (17 years now) Again, I made an assumption that I didn't clarify
(I guess it's no longer and assumption if I clarify it, is it?) I
NEVER use standard % Complete (duration % complete). Except on
entirely linear activities (like ditch-digging or a few other things),
it's meaningless. It is useful as a tool to calculate other indicators
in some instances, but not as a measure of real progress in most
instances. I always advise my clients/students to change over to %
Work Complete and work from there. I rarely care how many days have
passed since work started. I need to know how much work has been
accomplished against how much was supposed to be (EV). In fact, I
steer my clients away from using ANY % complete as an input to
progress. It's too easily influenced by pressure to reach a deadline.
I encourage them to use it as a reporting tool only.
Thanks for the clarification.