K
Keith
I'm using Project 2003 and I'm looking for ideas on how to best handle
overlapping tasks. Here is the scenario:
Task 1 has a duration and work of 50 hrs
Task 2 work hrs are 10
Task 2 must start 5hrs after the start of Task 1
Task 2 must finish 5 hrs after the finish of Task 1
It appears I can only link Task 2 to Task 1 once, either the start or the
end. However, if I link Task 2 to the start of Task 1 and the duration of
Task 1 changes then the duration and end of Task 2 is no longer correct.
Conversely, if I link the end of Task 2 to the end of Task 1 and the duration
of Task 1 changes, then the start and duration of Task 2 are incorrect.
Anyone else faced this issue?
overlapping tasks. Here is the scenario:
Task 1 has a duration and work of 50 hrs
Task 2 work hrs are 10
Task 2 must start 5hrs after the start of Task 1
Task 2 must finish 5 hrs after the finish of Task 1
It appears I can only link Task 2 to Task 1 once, either the start or the
end. However, if I link Task 2 to the start of Task 1 and the duration of
Task 1 changes then the duration and end of Task 2 is no longer correct.
Conversely, if I link the end of Task 2 to the end of Task 1 and the duration
of Task 1 changes, then the start and duration of Task 2 are incorrect.
Anyone else faced this issue?