Overtime at 1.5 & then double time after 55 hours

B

Bert

hi all,
I know how to assign overtime but after 55 hours per week the overtime is
double (60 hours total work per week, 40 regular then 15 hours at 1.5 then 5
hrs at double)
Can Project 2003 do this (or 2007)?
Or is there an easy work around?
thanks for any suggestions
Bert
 
R

Rod Gill

HI,

Sorry, no. Project only has one overtime rate. If you have to get costs
accurately, you can fudge the result by using two resources, the second one
for Resource at double-rate for the 5h.

--

Rod Gill
Microsoft MVP for Project