Overtime setup

J

Junaid

How do u setup Overtime hours in the Project Server and on your project.
My goal is ..
1. User should be able to enter 8 hours work as a normal schedule and if
they spend more time, it should go to overtime hours.
2. User should be able to enter there the timesheet for weekend work, for
example replying to emails, working on excel files. etc. (how can i charge it
to overtime hours)
3. If i schedule a task to be completed in 3 days, and task starts on
Friday, its end day shoud be Tuesday, not Sunday.
(I have setup the standard calendar using the exception for saturday and
Sunday using this procedure.

1) Go to Tools>Change Working Time...
2) Click "Create New Calendar"
3) Copy the Standard Calendar
4) Go to the "Work Weeks" tab at the bottom of the form.
5) Click "Details"
6) Change Sunday and Saturday to be "Set day(s) to these specific working
times:" and put in 8:00 AM - 12:00 PM and 1:00 PM to 5:00 PM in the From, To
section.

)

What is the best way to achieve this scenario?
Thanks

Junaid
 
S

Sander

Hi Junaid.

You don't have to change the default calendar. A users is alway able to
report time in weekends. Also planning a 3 days task will end on tuesday with
the default calendar.
The thing with overtime reporting is that the users have to specify if work
done is normal time or overtime.
 