B
BTOjohn
Hi All,
Before I start, I want to aknowledge that the culture I describe here is not
one of a commercial organisation, rather it is closer to an academic
environment.
I've got an issue with overtime. Our organisation does not pay overtime, and
has had a history of staff recording only 1day of work in any one day. Since
many dedicated staff work very long hours, this did not represent the effort
being applied. We have changed this now, so people record the hours that they
do, which of course helps us attain more accuracy in accounts, aids in future
tenders etc etc. However, we have one or two people who have rightly pointed
out that this will heavily skew the time budgets, making it difficult to
guage how many funded days are left. eg historically, if 10 days of funding
were received, then the work would get done in 10 days, but only because
staff work on average, and by choice, an extra hour per day.
As a transitionary measure, I am hoping to somehow record for each day, if
it is more than 7.4hours, then it equals 7.4hours, and if it is less than
7.4hours, then it equals itself. These figures added up would give a fairer
comparison to baseline work. (one day of work is 7.4h)
I hope I have made myself clear, and I hope that someone out there can help!
Thanks in advance,
John
Before I start, I want to aknowledge that the culture I describe here is not
one of a commercial organisation, rather it is closer to an academic
environment.
I've got an issue with overtime. Our organisation does not pay overtime, and
has had a history of staff recording only 1day of work in any one day. Since
many dedicated staff work very long hours, this did not represent the effort
being applied. We have changed this now, so people record the hours that they
do, which of course helps us attain more accuracy in accounts, aids in future
tenders etc etc. However, we have one or two people who have rightly pointed
out that this will heavily skew the time budgets, making it difficult to
guage how many funded days are left. eg historically, if 10 days of funding
were received, then the work would get done in 10 days, but only because
staff work on average, and by choice, an extra hour per day.
As a transitionary measure, I am hoping to somehow record for each day, if
it is more than 7.4hours, then it equals 7.4hours, and if it is less than
7.4hours, then it equals itself. These figures added up would give a fairer
comparison to baseline work. (one day of work is 7.4h)
I hope I have made myself clear, and I hope that someone out there can help!
Thanks in advance,
John