Can we capture Overtime work (as opposed to Work) from the PWA Task Timesheet
view?

If so how?
 
C

Chris Marriott

Hi

Yes you can

Go to tasks in the Project Web Access client
Select the timesheet view from the task pane on the left
Click the view options tab
You can select the "Show Overtime Work" option

Hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 
S

SpiroT

Thanks Chris! Darn, this was driving me crazy!

Chris Marriott said:
Hi

Yes you can

Go to tasks in the Project Web Access client
Select the timesheet view from the task pane on the left
Click the view options tab
You can select the "Show Overtime Work" option

Hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 